What Counts as a Major Repair —
The Line Between Interior Work and Permitted Construction

LEA Architects · Junsu Kim, Architect

"It's Just Opening Up One Wall"

The most dangerous sentence in renovation consultations. If that wall is a load-bearing wall carrying structural load, opening it up becomes a major repair under the Building Act. Major repair is the boundary line between interior work and building permitting — cross it, and you need design documents and a permit or report.

The line looks blurry, but the law lists the items clearly. Here's the essential summary.

Major Repair Determination Items (Building Act Enforcement Decree Art. 3-2, summarized) Load-bearing wall Add/remove, or repair/alter 30㎡ or more of wall area Columns · beams · roof trusses Add/remove, or repair/alter 3 or more of each Fire wall · fire-compartment floor and wall Any addition, removal, repair, or alteration Main / evacuation / special evacuation stairs Any addition, removal, repair, or alteration Boundary wall between units (multi-household/multi-unit) Any addition, removal, repair, or alteration Exterior finish material Add/remove, or repair/alter 30㎡ or more of wall area Matches above = Major Repair → Permit (in principle) / under 200㎡ & 3 stories = Report Non-load-bearing partitions, wallpaper, flooring finishes are NOT major repair
Major repair items summary (see Enforcement Decree text for exact wording)

The Real Weight of Major Repair — Current-Code Retroactivity

The burden of major repair lies less in the procedure than in what follows. The moment a major-repair permit is triggered, current fire and evacuation codes apply, which can require a firefighter access window or fire-rated reinforcement that didn't originally exist. Exterior finish change made the list precisely because of fire-spread prevention.

Our completed Jungdong remodeling in Giheung-gu, Yongin is a textbook example. In a project converting a neighborhood facility into an academy, the use change triggered current code, cascading into fire-rated gypsum board reinforcement, a new firefighter access window, and accessibility-facility installation. This is exactly where an "interior budget" becomes a "construction-permit budget." View this project →

Pre-Construction Checklist

① Confirm via drawings whether the wall to be demolished is load-bearing (site survey if no drawings) → ② Determine whether it matches a major-repair item → ③ If so, determine permit vs. report (permit vs. report guide) → ④ Budget for retroactively applied fire/evacuation items. Especially if construction follows a commercial lease, this review must be completed before signing. (Pre-lease building checklist)

Frequently Asked Questions

Q. What is a major repair?

Substantial repair/alteration of primary structural parts or exterior form. Items include load-bearing walls, columns/beams/roof trusses (3+), fire compartments, evacuation stairs, unit boundary walls, and exterior finish material change.

Q. Is a major repair a permit or a report?

In principle a permit; under 200㎡/3 stories it's a report. Either way, design documents and current code apply.

Q. Can interior work trigger a major-repair requirement?

Often. A load-bearing wall you want to open is a major repair; exterior finish changes qualify by scale too. Confirming load-bearing status before demolition is essential.

Major Repair Standards · Major Repair Permit/Report · Load-Bearing Wall Demolition · Exterior Finish Change · Remodeling Permit · LEA Architects